11 August 2015
The Eighth Arbitration Court of Appeal overturned the first instance judgment and awarded the monetary funds to a contractor – client of LF “KONUS” for the works work on the reclamation of the plots of the deposits completed in 2013.
The court agreed with the arguments of the appeal prepared by the partner of the Law Firm “KONUS” Sergey Mezhin regarding the complete and quality performance of the works and violation of the adversarial principle of the Parties by the Court of First Instance, and recovered 14 million rubles.
Return to news list